Brief
OO Group engaged us to carry out an internal re-stack project for AlixPartners within Level 6 at New Street Square. Works consisted of removing existing partitions, furniture, doors and glazing, then installing new partition walls and glazed partitions for exec offices, a kitchen area and workspaces, ceiling repairs and drop-down bulkheads to suit the new layout. Power adaptions were made for desk moves along with some furniture installation.
The works were challenging as everything had to be done outside of normal working hours and within a ten-day timeframe, meaning extra staff alongside our core team working long shifts to hit the deadline.